Contact info gathering plan
|
- 1 day 7 hours working hour
|
- Available Manpower : 5 persons
|
- it is estimated that within 1 hour we can probably
get average of 6 contacts
|
- It is estimated that total of about 210 contact
information per day can be gathered
|
- Total day needed for 1000 manufacturers contacts
is about 6 days
|
- At the end of the week, all 1000 contacts should be
emailed and depend on the budget allocation 1000 survey set must be folded
and posted
|
-photocopying and folding should run concurrently with
contacting respondent
*This Plan apply to either group of Manufacturer or LSP.
There are 720 LSPs
Dates of Mailing Questionnaire and follow up waves is as drafted in the following link: http://nlsproject.blogspot.com/2013/10/waves-dates.html |